RSA 146-C:7 New Facilities.

Title: X - PUBLIC HEALTH Chapter: 146-C - UNDERGROUND STORAGE FACILITIES

I. Prior to commencing construction or installation of a new facility or substantial modification of an existing facility, an owner shall submit plans and specifications to the department and obtain written approval of those plans. Such plans shall be approved by an engineer licensed to practice in the state of New Hampshire on forms provided by the department. Within 90 days of submission of completed plans, the department shall send the owner written notice of approval or disapproval. Failure to send a notice shall be deemed to be approval of the plans.
I-a. Any person, except state and local governments, including counties, and school districts, submitting plans and specifications for a new facility shall pay to the department a fee of $100. Such fee shall be for reviewing