RSA 155-E:5 Minimum and Express Reclamation Standards.
Title: XII - PUBLIC SAFETY AND WELFARE
Chapter: 155-E - LOCAL REGULATION EXCAVATIONS
Within 12 months after the expiration date in a permit issued under this chapter, or of the completion of any excavation, whichever occurs first, the owner of the excavated land shall have completed the reclamation of the areas affected by the excavation to meet each of the following minimum standards or when such excavation is not subject to a permit under this chapter pursuant to RSA 155-E:2, to meet each of the following express standards:
I. Except for exposed rock ledge, all areas which have been affected by the excavation or otherwise stripped of vegetation shall be spread with topsoil or strippings, if any, but in any case covered by soil capable of sustaining vegetation, and shall be planted with seedlings or grass suitable to prevent erosion. Areas visible from a publ