RSA 674:75 Advance Pipeline Notification.
Title: LXIV - PLANNING AND ZONING
Chapter: 674 - LOCAL LAND USE PLANNING AND REGULATORY POWERS
I. As used in this section, "natural gas transmission pipeline" means an interstate pipeline, as that term is defined in 15 U.S.C. Section 3301(15); and
II. For a new residential or nonresidential development that is located in whole or in part within 1,000 feet of the center point of a natural gas transmission pipeline that was constructed or operated prior to the development, the applicant shall notify the operator of the natural gas transmission pipeline of the planned development no later than the time of application for approval of the development, or 180 days prior to commencement of construction, whichever is earlier.
III. The developer of the development shall provide on a form filed with the local land use board the following notice:
"All reasonable means